Principle of legalityGovernment is only authorised to intervene via statuory law
Reactive powerGovernment reacts to private sector development initiatives via permits
Proactive powerGovernment takes development initiatives
Pre-emption rightsIf the owner of land sells, he has to offer it to the municipality first, a forced offer
ExpropriationThe municipality takes the land forcefully, in order for the good of the public with compensation if no agreement could have been made
territorial distributionpowers are spread across different sectors of territory, decentralisation
Functional distributionGovernmental powers not confined to one body but divided among several different ones, Trias politica
Functional decentralisationdistribution of powers through a combination of territorial and functional distribution
Public Lawregulates structure of the state and relationship between state and individuals
Private lawrelationships between individuals without direct involvement of the state
Right to developthe owner of the land has the right to realise building plans for that land
Development rightsthe exclusive right that one party received from another party, on the basis of agreement, to realise a certain program on a certain location
Compensation on base of-Direct and indirect damages -Capital and income losses -Several planning decisions -Irrevocability -No complete compensationjn -Monetary or in kind compensation
Planning compensation rights agreementagreement between developer and municipality for planning compensations that the municipality approves
Self-realisation principleif a party realises a land-use plan in accordance with the municipality his land cannot be expropriated
Private law restrictiona right which one landowner has with respect to the land of another, burden on land of neighbour which is favourable for yourr land
right of superficiesthe ownership of a building is seperated from the ownership of the land below it
Environmental permitGrants permission from authorities to steer building in their interests, preventive measure
Assesment frameworkStrict criteria based on: - Urban planning - Technical soundness and safety - Aesthatics - Health and environment
limitative-imperative systemCompulsory grounds for refusal
Compulsory ground for refusal of environmental permitIn conflict with: - Building Decree - Municipal building bye-law - Municipal land-use plan - Reasonable requirements of external appearance - Safety norm regarding road tunnels
lex silencio positivoShould the applicant after eight weeks not have received a response to his application, the permit is deemed to be granted
Municipal bye-lawContains regulations of different natures
Management regulationmeant for areas where no new spatial developments are anticipated. its purpose is the conservation of the area
Visual quality planThis plan offers judgements concerning the desired urban and architectual form and structure of a city
Site development planIn case of no consensus in private law the municipality will recover costs in public law via site development plan by: - developing a map - Planning - Budget - Recoverement of costs plan - Timetable
Master planSpatial planning plan with no legal force but has legal force in two scenarios: - Indirect via deviation from land-use plan by listening to master plan - Can have legal force under private law by being included in agreement
Interested partypartys that are directly influenced by a decision
Protective norm theoryPerson X cannot invoke violation of a rule if the rule did not intend to protect X
Testing of land-use planif obiding regulations and has principles of proper administration
Deviation of land-use planMunicipal executive decides however municipal council must issue a declaration of no objection.
Project implementation decisionJust one governmental decision satisfies to allow the whole project. taken by municipal council and overrules need of permits and is deviation of land-use plan if necessary
Structure visionLocal plan, which contains main elements of the spatial policy to be pursued. also includes how to realise the plan is administrive self-binding
Principle of equal treatmentThe government should treat even cases equally
Active land policy- Municipal acquisition of undeveloped land - Preparing the land for construction - Sale to developers
Ground leaseLeasing land while holding full ownership. could be accompanied with obligation to build, maintain and upkeep
Reasons for municipality to ground lease- Influence - Making money - Stimulating production of new buildings
Declaration of intentContract in which is laid down which conditions must be fulfilled before parties will enter into a further agreement
Partnership agreement contents- Arrangements of a financial nature - Settlement of costs - The program - Phasing and planning - The partnership model - A land purchase obligation - Financial means and public law powers
Development rights modelDeveloper sells land to municipality which municipality prepares for construction and sells back along with development rights
Joint-venture modelParties incorporate a legal entity so both parties share the risk, intended for large scale projects
types of public-private partnership- Contractual - Forming a legal entity
Land development companyMunicipality incorporates a company together with other parties, in which it holds shares. legal entity. they can independently participate in legal matters while risks are still shared
Land-use plan agreementAdapting land-use plan for developer based on an agreement
Development planningPrivate parties involved in planning and feasibility will be enhanced by this governement receives commitment
The infrastructure planning actImplementation of statuory limitation of the parties that have a right to oppose against infrastructure decisions before court
Research obligationto prove the aspect is considered to not nullify the decision
Environmental impact assesmentResearch on the impact of the project on the environment, broad focus
Strategic environmental assesmentpotential environmental effects of their plans and programmes mandatory for certain sectors
ZoningSpecific spatial distance is laid down in the land-use plan, to separate vulnerable objectives from nuisance objectives
Specific research obligation fields- Environmental noise - Air quality - External safety - Soil assessment - Water assessment - Nature conservation - Archaeological value assesment