Question:

This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom- up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.

Author: Mitch Palmer



Answer:

Definitive estimate