From course:
(Practice similar questions for free)
Chapter 1 - A new approach for complex problems
» Start this Course(Practice similar questions for free)
Question:
A Scrum Team is at the end of a Sprint. The next Sprint starts a) Only after the product Increment is released to production. b) Only after the Retrospective event of the current Sprint. c) Only after the team for the next Sprint is on board. d) Only after the Sprint Planning.
Author: Avinash UpadhyayAnswer:
B) Only after the Retrospective event of the current Sprint. The Product Owner may choose to release the Increment to production, but it is not mandatory. The same team will continue to work on the next Sprint. Sprint Planning is the first event of the Sprint. The last event of the Sprint is the Retrospective. Correct answer is ‘b.’
0 / 5 (0 ratings)
1 answer(s) in total