Question:
A Scrum Team can have an exclusive first Sprint to prepare a Product Backlog, which is the sole outcome from that Sprint. a) True b) False
Author: Avinash UpadhyayAnswer:
B) False A Scrum Team can initially work outside the Scrum Sprints to create and refine just enough of a Product Backlog so that the first Sprint can start. However, this initial effort should not be called a Sprint. Also, it should only take a few days. Correct answer is 'b.'