Question:

How does a Scrum Team define the Definition of Done? a) It always creates a new Definition of Done. b) It checks with the Product Owner if a Definition of Done is required and then proceeds to create one. c) None of the above.

Author: Avinash Upadhyay



Answer:

C) None of the above. If there is an existing Definition of Done (that is the organizational standard), Scrum Team must use it. Only when it doesn’t exist, Scrum Team must create a Definition of Done. Correct answer is ‘c.’