Question:

Select all that apply. The sprint review is an event that requires a) A product owner's sign off b) Active Participation of the Stakeholders invited by the Product owner. c) Transition Sign off d) Inspection & Adoption activities

Author: Avinash Upadhyay



Answer:

B) Active Participation of the Stakeholders invited by the Product owner. d) Inspection & Adoption activities Sprint Review doesn't require any formal sign-offs as it is an informal meeting to elicit feedback and foster active collaboration between all participants. Correct answers are b & d