Question:

A good guidance to differentiate acceptance criteria from the Definition of Done is the Definition of Done provides a checklist of Quality measures to take the increment to a potentially usable state, while acceptance criteria focus on specifying the Business features(Functionally ) a) True b) False

Author: Avinash Upadhyay



Answer:

A) True The Definition of Done is a commitment that defines the Quality measures for a usable increment (Fitness for use). Acceptance Criteria are the specification of the expected Business features (Fitness for Purpose). Correct answer is "a"