Question:

A scrum team maintains a Sprint Burn Down chart to track estimated remaining work. In the Middle of the Sprint the Burn down graph shows an upward spike. This indicates a) A planned work is removed b) The Product owner added new item to the Sprint. c) The Developers added new Work.

Author: Avinash Upadhyay



Answer:

C) The Developers added new Work. A spike indicates the added work. The Product owner cannot add new work without the developers consent. Correct answer is "c"