Question:
An important executive wants the developers to take in a highly critical feature in the current sprint. The Developers a) Should work on that since the organization's priority is more important. b) Should ask the executive to work with the Product owner c) As an empowered team they should ask the executive to select the work to be removed so that there will be the same amount of work in the sprint.
Author: Avinash UpadhyayAnswer:
B) Should ask the executive to work with the Product owner