Question:

In the middle of the sprint a team member was required by another department manager to support an important task outside the Sprint work. What is recommended for the team member to do? a) The team member must support since it is important task. b) The Team member should ask the manager to speak with Scrum Master. c) The Team member should politely decline and explain to the manager his responsibility and accountability to the Scrum team

Author: Avinash Upadhyay



Answer:

C) The Team member should politely decline and explain to the manager his responsibility and accountability to the Scrum team