Question:
When is the Product backlog retired? a) when the Product owner retired. b) When all the sprints are over. c) When the Product retires. d) When a customer provide sign off on the Completion of the Project.
Author: Avinash UpadhyayAnswer:
C) When the Product retires.
0 / 5 Â (0 ratings)
1 answer(s) in total