Question:
Which is not the product backlog management activity? a) Clearly expressing and ordering Product backlog items. b) Optimizing the value of the work of the Developers. c) Using formal change control to manage product backlog when the market provides feedback from product usage. d) Ensuring the developers understand items in the product backlog to the level needed.
Author: Avinash UpadhyayAnswer:
C) Using formal change control to manage product backlog when the market provides feedback from product usage.