Question:
At the end of the Sprint planning, the Developers could not decompose all the work into units of one day or less. It could only decompose the work only for first few days of the sprint. a) The Developers should close the sprint planning and start the work. b) Since the team is self managing, they should continue sprint planning in the following days before they start the work. c) The Scrum master should coach the team in the Required skills.
Author: Avinash UpadhyayAnswer:
A) The Developers should close the sprint planning and start the work.
0 / 5 Â (0 ratings)
1 answer(s) in total