Question:

What actions should you take as phase 2 (during risk workshop) of a risk analysis workshop?

Author: Debbie Smith 447c



Answer:

•Have a short presentation for project scope, its current status, risk management process, project specific requirements, objectives of the workshop, agenda, •Focus on top risks first then low risks •Use available time during workshop for risk identification and high level analysis. •Differentiate between “Issues” and “Risks”.