Question:
Is it possible that you come across different story points for development and testing efforts? In that case how do you resolve this conflict?
Author: Ed HowardAnswer:
Yes, this is a very common scenario. There may be a chance that the story point given by the development team is, say 3 but the tester gives it 5. In that case both the developer and tester have to justify their story point, have discussion in the meeting and collaborate to conclude a common story point.